Last year the City Council approved an ambitious new two-year work plan that addresses our many priorities in a methodical and deliberate approach.
Infrastructure
- Developing a A Ten Year Capital Improvement Plan (FY2019)
- Developing a Ten Year ADA Compliance Plan (FY2019)
- Develop a Storm Water Master Plan (FY2019-20)
Public Safety
- Implement a Community Policing Strategy (complete)
- Enhanced use of technology (FY2019 – underway with use of drones, cameras, and gunshot geolocating technology)
- Restore UCFD Ambulance Service and Mutual Aid (FY2019 – underway and estimated to begin in late 3rd quarter of 2019)
- Accreditation of Police Department (FY2019-22 – underway)
Economic Development
- Olive and I-170 Development (FY2019)
- Develop an Economic Development Strategy (FY2019 – underway)
- Parking Study to Analyze Parking in the Loop and WU Parking Impacts (FY2019 – underway)
- Hotel Feasibility Study for Olive and Delmar at I-170